During the installation of a bolted coupling, what is done after stabbing the coupling to the mark?

Prepare for the NGA 29/30 Repairing a Distribution Pipe Test. Use flashcards and multiple choice questions to enhance comprehension. Engage with hints and explanations for every question. Gear up for your exam success!

After stabbing the coupling to the mark during installation, the next crucial step is to inspect the joint according to manufacturer instructions. This inspection is vital to ensure that the coupling is properly aligned and seated. By following the manufacturer's guidelines, you can confirm that there are no issues that could lead to leakage or failure of the joint later on.

This step typically involves checking for correct positioning and making sure that the surfaces are clean and free of debris. Conducting this inspection minimizes the risks associated with improper installation, such as misalignment or inadequate sealing, which are critical for maintaining the integrity of the distribution pipe system. Following the manufacturer's instructions ensures that you are adhering to best practices specific to the coupling being used, increasing the reliability and longevity of the installation.

Other steps like performing a soap test, applying protective coatings, or torquing the bolts are important but typically occur after the initial inspection to ensure that the coupling is ready for these subsequent actions.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy